Do I Need a Permit? Yard Projects in Hamilton and Burlington
Lumen Landscaping
Most yard work in Hamilton and Burlington needs no permit: a patio on the ground, a walkway, new sod, garden beds and a fence within the height limits are all yours to build. What does need an approval is a short list: some retaining walls, most raised or attached decks, pool and hot tub enclosures, bigger changes of grade, a wider driveway across the City boulevard, work near protected trees, and almost anything on a lot a conservation authority or the Niagara Escarpment Commission regulates.
This guide gathers those rules in one place, each with a link to the City or authority page it comes from. We checked every one on November 25, 2026; by-laws change, so the source page and the staff it names have the final word. We build landscaping and hardscaping across both cities and tell you before we quote whether your project needs anything, but the approvals themselves come from the City and the authorities below.
Retaining walls
Hamilton. The rule comes from the Ontario Building Code (Division A, Article 1.3.3.5). A retaining wall over 1,000 mm of exposed height is a designated structure when it is next to public property, the access to a building, or private property the public is allowed onto, and a designated wall needs a building permit and an engineer’s design. A garden wall between two back yards is usually not one, but height is not the only question: the City’s site alteration page says a retaining wall, new hard surfaces or a drainage fix may need a site alteration permit (see grading, below), and a creek or escarpment lot can need the conservation authority first.
Burlington. The City’s building permits page lists a retaining wall 1 m high or less among the projects that need no building permit. Its site alteration screening checklist, though, asks whether you are installing a retaining wall at all, and a yes means you likely need a Site Alteration Permit under By-law 64-2014.
What keeps a wall standing is a different question from what the City approves; see retaining walls, why a retaining wall leans and our retaining wall ideas for a sloped yard.
Fences
Hamilton. No building permit is needed for a fence unless it encloses a pool. Fence By-law 10-142 sets the heights:
- 2.0 m on a residential lot
- 0.9 m inside a corner visibility triangle (5.4 m along each street line from the corner), a driveway visibility triangle (2.7 m along the driveway edge and the street line), or within 3.0 m of the front lot line
- Up to 2.4 m for a section no longer than 4.5 m that stands at least 1.2 m from a side lot line and 3.0 m from the rear lot line; on a deck, with the same setbacks, 2.0 m above the deck floor
- A gate may go 0.3 m over the limit, an archway 0.4 m, and a decorative cap or post 0.15 m
- On top of a retaining wall, the height is measured from the top of the wall
The City’s Residential Fences page adds that a fence has to stand on your own land unless you and your neighbour agree to put it on the shared line, and that disputes between neighbours are a civil matter.
Burlington. In the residential zones, fence heights now come from the Residential Zoning By-law 09-2026, in force since March 2, 2026:
- 2.5 m for residential uses, measured from grade to the top of each 3 m section
- 1.2 m within 3 m of the front lot line (2.5 m along the shared line where a front yard meets the rear yard of a corner lot)
- 0.3 m more where the ground slopes, as long as the low end of the section stays within the limit
- 1 m for solid fencing and landscaping inside a visibility triangle: 6 m by 6 m at a street corner and 3 m by 3 m where a driveway meets the street
- 1.8 m for a privacy screen on a deck or porch, measured from its floor
The previous by-law’s figure was 2.0 m, and you will still see it in older handouts, so check with the City’s zoning staff for your lot. See fences and gates.
Decks
Hamilton. The City’s Porches and Decks page requires a building permit for any deck attached to a building, a deck used with a swimming pool, a detached uncovered deck over 10 square metres and more than 200 mm above grade, a detached covered deck over 10 square metres, and a small detached deck at a door that is more than 600 mm above grade. Replacing or adding guards, the code’s word for railings, also needs a permit. A deck that needs no permit still has to meet the zoning by-law.
Burlington. A deck needs a permit if it is connected to the house or another structure, if a detached deck is over 10 square metres, if it is more than 600 mm above grade, or if it is covered (Decks, Porches and Patios). An uncovered patio on grade needs no building permit. Before the building permit comes a pre-building approval, the City’s zoning check.
Deck stairs with decorative privacy panels
More on building them: decks and fences.
Pools, hot tubs and their enclosures
We do not build pools, but the rules around them shape the fence, the deck and the patio beside one.
Hamilton. No building permit is needed to install a pool, but one is needed for the pool enclosure (the fence) and for a deck in addition to or adjacent to the pool, and the pool cannot be filled until the enclosure is in place and approved (Swimming Pools). Under Swimming Pool Enclosure By-law 16-184 an enclosure is at least 1.5 m high, and a hot tub that can hold water more than 0.6 m deep counts as a pool: it needs a rigid cover able to carry 90 kg, fastened and locked when not in use, or an enclosure. The site alteration exemption for a permitted pool limits any retaining walls to 0.5 m and, where no grading plan was approved, keeps a 60 cm strip of undisturbed ground along the rear and side lot lines in the back yard.
Burlington. A permit comes before any pool, swim spa or hot tub (Pool Permits). A pool goes through one combined application for zoning, a tree permit and the enclosure; a hot tub under 8 square metres has its own permit, and no water goes in until its fence or lockable lid has been inspected. The zoning keeps a pool out of the front yard, 1.5 m from a lot line to the pool’s inside wall and 0.9 m from a lot line to the edge of its hard landscaping.
Wood and metal picket fence with a river rock border
For the base under a tub, read hot tub pads and shed bases.
Grading, fill and lot grading plans
Hamilton. Site Alteration By-law 19-286 covers bringing in or digging out fill or topsoil and changing the grade. Landscaping, lawn work and gardening are exempt when no more than 15 cm of fill goes down anywhere, the drainage onto neighbouring properties does not change in location, direction or rate, and no swale is changed or blocked. The City says exemptions are confirmed in writing by its staff, at no fee, and that a lot whose final grading has not been certified needs a site alteration permit, no exceptions. A permit takes about four to six weeks from a complete application.
On the City’s Lot Grading and Drainage page, the homeowner is responsible for keeping the grading the City approved when the subdivision was built. Swales, the shallow grassed channels along the lot lines, must not be filled or blocked, and rear yard catch basins must stay open. The current owner can ask the City for a copy of the lot’s grading plan.
Burlington. Site Alteration By-law 64-2014 regulates filling, grading and excavating, and the City names pool installation, yard landscaping or infilling, sidewalk and patio construction and retaining walls as projects that can need a permit. The screening checklist asks about any change of grade within 0.5 m of a property line and fill less permeable than the native soil. When a building permit is involved, the Grading and Drainage Clearance Certificate comes first, and the City’s design criteria cap hard surfaces at 50 to 60% of the lot, depending on frontage.
See grading and a sloped backyard you cannot use.
Downspouts
Hamilton’s Sewer and Drain By-law 23-234 added required disconnection of downspouts, so roof water stays out of the sewer. For eligible homes, the City’s Protective Plumbing Program lists downspout disconnection as grant work, done through its pre-qualified contractors. Once a downspout empties onto the yard, the lot grading rules above apply: the water must not run back to the house or onto the neighbour. That part is ours; see yard drainage.
Driveway widening and curb cuts
In Hamilton you need the City’s access approval to build or widen a driveway across the boulevard, approaches run 2.7 to 3.6 m for a single and 5.4 to 6.1 m for a double, the City builds the approach ramp itself, and a 50% green space requirement means you cannot pave the whole front yard. In Burlington a driveway modification permit comes before any widening, the curb and sidewalk work is arranged by the City, and the width allowed depends on your frontage. The details are in our guide to widening your driveway in Hamilton or Burlington.
Trees
Hamilton. Under Tree By-law 15-125, a public tree permit is needed before any work that may affect a City-owned tree, and a tree with more than half its trunk at ground level on your side of the line is yours (Tree Ownership and Responsibilities). Ancaster, Dundas and Stoney Creek have by-laws for private trees, as do woodlots, so work that affects one there may need a permit; the former City of Hamilton has none.
Burlington. The Public Tree By-law 098-2025 needs a permit to injure or remove any public tree. The Private Tree By-law 040-2022 applies inside the urban boundary: injuring or removing a tree 20 cm or more across at 1.37 m above the ground needs a permit, and work inside its minimum tree protection zone counts as injury. That zone is 1.8 m for a trunk under 10 cm, 2.4 m from 11 to 40 cm, 3.0 m from 41 to 50 cm and 3.6 m from 51 to 60 cm, growing with the trunk. Pruning no more than a third of a private tree’s live crown needs no permit.
Taking a tree down is an arborist’s job, not ours. Read tree roots lifting a walkway for building beside one.
Conservation authorities and the escarpment
Four conservation authorities share Hamilton, and the City’s Building Permit Application Requirements page names them: the Hamilton Conservation Authority, Conservation Halton, the Grand River Conservation Authority and the Niagara Peninsula Conservation Authority. Burlington is Conservation Halton’s. Each regulates land near watercourses, wetlands, valleys, steep slopes and the shoreline under Ontario Regulation 41/24. Conservation Halton defines development there to include decks, sheds, stairs, retaining walls, site grading and placing or removing fill, and its permission does not replace the City’s permits. The Hamilton Conservation Authority notes exemptions for some non-habitable accessory structures and detached decks, with size and location limits, and posts its regulated area maps online. Our Waterdown, Flamborough and Binbrook and Glanbrook pages say which authority covers which creek.
On the escarpment, the Niagara Escarpment Commission issues a development permit in its Area of Development Control, including for altering the grade of land and bringing in soil. Its interactive map shows whether a lot is inside, and Hamilton’s permit page notes that such land needs the Commission’s development permit to be developed.
Locates before any digging
By law, anyone who digs in Ontario must first contact Ontario Dig Authority, the name Ontario One Call took on October 1, 2026; its services and requirements stayed the same. The locate is free, and the request goes in at least five business days before the dig. Each utility then marks its buried lines. A fence post, a deck footing and a new tree all count as digging.
Frequently asked questions
Does a patio or a walkway need a permit?
Usually not a building permit: Hamilton lists landscaping, and Burlington an uncovered patio on grade, among projects that need none. A grade change can still need a site alteration permit, and Burlington names sidewalk and patio construction among the projects that can.
Does a shed need a permit?
In Hamilton, a shed, garage or gazebo over 15 square metres needs a building permit; one up to 15 square metres, one storey and without plumbing does not. Burlington exempts one storey sheds under 15 square metres with no plumbing. Zoning still decides where it can sit. For the base, read hot tub pads and shed bases.
Who applies for the permit?
The owner, or someone the owner authorizes: Hamilton’s online portal takes applications from the owner or an agent acting for the owner. We tell you before we quote what your project needs and build it to the approval you hold.
Where these rules come from
Every rule above links to the City, provincial or authority page it comes from, and each was checked there on November 25, 2026. The retaining wall rule is Division A, Article 1.3.3.5 of the 2024 Ontario Building Code. If a page has changed since, the page wins.